Commercial induction power: kW, phase and circuits, decided in that order

Most mistakes in commercial induction projects happen in the wrong order. Buyers start with "how many hobs", then discover the supply cannot carry them. The order that works is: fix the power per hob from the cooking method, then decide single-phase or three-phase from the number of hobs and the supply available, then size the circuits, and only then count hobs. Get the first step wrong and every later decision inherits the mistake.

Step 1: power per hob comes from the cooking, not from the budget

Cooking stationWhat drives the ratingSignal you under-sized it
Tea, soup, holding, light sautéPan reaches temperature and holds it; recovery between dishes is slowWater takes too long to return to a boil after a batch is served
Wok and stir-fryHigh temperature for short bursts and fast recovery between ordersThe pan cools visibly when food goes in, and the next dish starts late
Rapid boiling, noodles, stockLarge water volume brought up and kept rollingRolling boil drops to a simmer when a second basket is added
Multi-hob counterSum of the stations plus whether they run togetherThe breaker trips when two hobs are at full power

Power is not a quality ranking. A higher rating on a poorly coupled pan performs worse than a lower rating with the right pan diameter and flat base. Induction heats the pan, not the air, so pan material, base flatness and diameter against the coil matter as much as kW.

Step 2: single-phase or three-phase

Voltage and plug type must be fixed before production, not after. A 220V unit cannot simply be rewired to three-phase on arrival, and a plug that does not match the site becomes a local electrician's problem on installation day.

Step 3: circuits, breakers and earth

  1. One dedicated circuit per unit, with its own breaker and earth connection. Sharing a circuit between two high-power hobs is how a fault takes down the whole line.
  2. Residual current protection on the kitchen circuits, sized to the unit, not to the room.
  3. Cable and breaker sizing from the actual rating, computed by a local electrician against local code. The appliance nameplate gives the input; the installation rules come from your jurisdiction.
  4. Earth continuity verified at commissioning, per unit, and recorded. This is also the check that matters if a warranty claim is ever disputed.

Replacing gas in an existing kitchen

The four things that break a retrofit are, in order: total connected load against the supply you actually have; simultaneous-use factor — the nameplate sum is almost never the real peak, and sizing for the sum overspends while sizing for nothing overloads; cable and breaker capacity in the existing board; and counter strength plus ventilation around the units. Bring the unit ratings to your electrician before you order, not after the container arrives.

How we work

WECHGOOD builds commercial induction and infrared units in Foshan across single-hob and multi-hob configurations, with the voltage, plug and phase fixed at order stage because they cannot be changed later. Base certification — CE, CB, RoHS and ErP — is carried by us; certifications outside that set are quoted separately when your market requires one. Standard MOQ is 1,000 units per model, stock samples ship in two to three days, a customised sample takes about a week, and production runs 35 to 40 days. Send the cooking stations, the supply you have and the market, and the configuration is answered in the quotation rather than guessed on a call.

Common questions

Is a higher kW always better?

No. Above the rating the pan can absorb, extra power becomes heat in the coil and the electronics. Match the rating to the pan and the cooking method, then confirm the supply can carry it.

Can one circuit serve two hobs?

Not for high-power units. Two dedicated circuits cost little at installation and avoid a single fault stopping both stations during service.

Can you supply 110V for my market?

Voltage is fixed at order stage, so tell us the destination market and the site supply before the order is placed. Changing voltage after production means a new build, not a rewiring.

What do you need from me to quote a commercial configuration?

The cooking stations and expected dishes per hour, the supply available on site (single or three phase and its capacity), the destination market and the certification you must show, and the annual volume. From those four we return the power per hob, the phase arrangement and the MOQ.

Sourcing terms at a glance

The same figures appear across every page of this site, so you can quote them when comparing suppliers.

ItemWECHGOOD terms
MOQ per model1,000 pcs
Samples1 pc; stock models ship in 2–3 days, customised samples in about a week
Lead time35–40 days after deposit
Base certificationsCE / CB / RoHS / ErP / UKCA
Factory18,000+ m² self-owned plant, Ronggui, Shunde, Foshan, Guangdong
Capacity5 production lines, 300+ workers, 15,000 pcs/day — 450,000 pcs/month
Burn-in2–4 hours on every batch
Reliability aging1,000 hours on qualification units
ToolingPaid by the buyer, rebated once the agreed volume is reached
Business modelManufacturer, OEM / ODM

Related sourcing guides

Foshan factory, direct

Send your stations and your supply

We will come back with the power per hob, the phase arrangement and the certification list for your market.